Integra Set a Mining Record, Then Cut Guidance — Because the Pad Couldn't Keep Up

Florida Canyon's 97,428 tonnes-a-day quarter produced a second downgrade to 2026 output, three months after the COO said he was 'very much so' comfortable with the number
ITR.V · Earnings Call · 2026-11-12

Integra Set a Mining Record, Then Cut Guidance

Integra Resources had a genuinely good operating quarter at Florida Canyon and then told investors the year would be smaller than promised. Both things are true. Q3 2026 produced 17,652 ounces of gold, up 8% quarter-over-quarter and 40% above Q1, at a record mining rate of 97,428 total tonnes per day. And on the same call, 2026 production guidance came down from 70,000–75,000 ounces to 59,000–62,000 ounces.

The mechanism is not a broken orebody, a permitting problem, or a missed grade. It is a stacking rate problem: Integra mined and stacked ore faster than its heap leach pads could leach it. “Recent leaching rates have not kept pace with the higher mining rates we've been running this year as we strip the higher-grade ore body in the Central Pit.” — Cliff Lafleur, Unknown · 2026-11-12 That is the sentence that matters. The record headline and the downgrade are the same fact.

The record that broke the pad

The quarterly mechanics are worth walking through, because they explain why the fix is slow. The company mined 5.3 million tonnes of ore and 3.6 million tonnes of waste at a strip ratio of 0.68. Gold recovery averaged 52.5%, down roughly five points as more run-of-mine material displaced crushed ore on the pad. Site all-in sustaining costs were $3,059 per ounce sold, below revised guidance, with cash costs of $2,419 per ounce — with leaching economics being squeezed by diesel, labour and explosives.

Revenue was $72.4 million against $49.1 million of cost of sales, a 32% mine operating margin. The company sold 16,760 ounces at an average realised $4,272 per ounce versus 20,265 ounces at $3,464 a year earlier — a reminder that the rising gold price is doing enormous work here, masking a 17% drop in ounces sold. Operating cash flow fell to $21.8 million from $35.6 million, free cash flow to $11.1 million from $20.2 million, largely on a $16.3 million working capital build from inventories.

The root cause is physical.

We learned pretty quickly that pads at Florida Canyon have historically, in the market a few years ago, were built very small. So you do not have a lot of room to maneuver and not a lot of flexibility when you are trying to do things like blend.

Cliff Lafleur, Unknown · 2026-11-12
With a small pad and variable fines, the blending that a leach curve needs became unmanageable at the mining rates the new fleet could deliver. Cliff Lafleur put it plainly: “balancing the blending of fines with the higher production rates as we ramped up became too difficult to maintain the leaching rates. We backed off the mining.” — Cliff Lafleur, Unknown · 2026-11-12

Hence a revised guidance that implies something the press release does not: with 46,666 ounces produced year-to-date, the new 59,000–62,000 ounce range implies Q4 of roughly 12,300–15,300 ounces — at or below Q1's level, before the whole ramp began. Lafleur conceded the stacking rate would revert to “more like what we were doing in Q1, Q2.” — Cliff Lafleur, Unknown · 2026-11-12

Three months ago, the same question got a different answer

This is the second revision in a year, and the sequencing is the uncomfortable part. On the August call, Joseph Reagor asked directly whether the team was still comfortable with full-year guidance given the slow start. The answer was a two-word headline:

Very much so. But again, I am going to address that question to Clifford. He's got the same level of high conviction as we all do with respect to our production guidance for the year.

George Gregory Salamis, Chief Executive Officer · 2026-08-12
Lafleur then explained that the newly delivered trucks and shovel let the company keep older units running: “we feel comfortable that we have the capacity to increase the tonnage rates and are watching it very closely and pleased with the results so far.” — Clifford Lafleur, Chief Operating Officer · 2026-08-12

And Lafleur explained the cost side that day in a way that now reads as a warning rather than a comfort: “The cash cost guidance went up this year because of the increase in tonnage. Stacked and treated on heap leach pads. That should start to calm down in 2027 as we access the new mining area in the central pits.” — Clifford Lafleur, Chief Operating Officer · 2026-08-12 The tonnage increase was the problem then too — it just had not yet shown up in ounces. What changed is that the constraint moved from cost per ounce to ounces themselves.

Management was also candid that capital would be back-end loaded: “it is not going to be an easy feat, but we are planning to definitely, we will achieve the stripping that we have planned.” — Clifford Lafleur, Chief Operating Officer · 2026-08-12 They largely did. Sustaining capital of $10.6 million in Q3 is elevated and guided to stay that way into Q4, but stripping to access the Central Pit stayed on schedule, which is the reason there is a 2027 story at all.

The ounces are on the pad — and the fix is a crusher

George Salamis was emphatic that this is a timing deferral. “They are on the pad. They are just leaching slower than we expected, and they will get recovered over the course of time.” — George Salamis, President and CEO · 2026-11-12 That is the bull case in one sentence, and it is credible for a leach operation — but it also means the company is carrying inventory it cannot sell into a $4,272 gold price this year.

The structural fix is the most interesting thing said on the call. Integra holds a permit allowing 14 million tonnes of crushing but has site capacity for only eight. “we have a 14 million ton crush limit on our crushing, and we only have capacity on site for eight... we should be doing more crushing. That is a no-brainer.” — Cliff Lafleur, Unknown · 2026-11-12 More crushed ore means faster kinetics and less dependence on blending run-of-mine fines — precisely the variable that broke 2026. Detailed engineering is budgeted for 2027, alongside the accelerated heap leach pad expansion that adds the blending room the operation never had.

Exploration supports the same arc. The Central Pit Radio Tower Saddle target returned 1.3 g/t over 62.5 m and 0.59 g/t over 167.6 m within the existing mine footprint, with 54 holes and 5,400 m planned — near-surface higher grades that could extend the leach feed. Meanwhile Nevada North and DeLamar carry the mid-tier gold producer ambition: the Record of Decision at DeLamar is targeted for the second half of 2027, long-lead orders are slated for year-end, and GenCap has been retained as financing adviser. Cash of $119.5 million and $159.5 million of working capital is the balance sheet that lets them wait.

What to watch

The balance sheet is real, the gold price is generous, and the development pipeline is genuinely advanced. But Integra has now told investors twice in one year that a guidance line was safe and then moved it, and the explanation both times traced back to the same choice: mining faster than the leach circuit could absorb. Watch the Q4 stacking rate against the Q1–Q2 cadence, the 2027 cost guidance they declined to give, and whether the crushing study converts from no-brainer to a purchase order. Until the pad catches up with the fleet, leach rates are the entire thesis.