McEwen Stops Blaming the Ore
A third straight Gold Bar shortfall finally gets a human explanation, the Los Azules calendar slides right again, and the shares arrive 37% off their August high.
MUX · Earnings Call · 2026-11-10
A geological alibi runs out
For three consecutive reports, the missing ounces at Gold Bar arrived with a geological explanation. In November 2025, Rob McEwen told investors the shortfall “appears to be a matter of sequencing and not a large risk” — Robert McEwen, Chairman and Chief Owner · 2025-11-06. By August 2026 the story had moved into the rock itself — COO William Shaver described carbonaceous material that “didn't reconcile with the resource model” — William Shaver, Chief Operating Officer · 2026-08-06. Different quarter, same mine, same reassurance. Q3 2026 broke the pattern, but not because the numbers got better. Ian Ball did not soften it: “it was a very difficult quarter. I would call it a very unacceptable quarter” — Ian Ball, Executive Vice Chairman · 2026-11-10. Then, instead of pointing at the block model, he pointed at the org chart:That is a materially different admission. Geology is an act of God; oversight is an act of management. It also means the fix is slower than a re-leach — Ball conceded that because Gold Bar is a heap leach and not a mill, “it does take time for those changes to take effect.” What followed was a quarter of mostly self-inflicted wounds stacked alongside one genuine weather event. At the Fox complex, nearly all of the Froome development spend landed in a single quarter while the mill was topped up from a low grade stockpile to fill excess capacity — two temporary items that nonetheless wrecked the reported cost base at the same time. And at San Jose, the company found a keyword it has never used before: moisture. The Andes delivered record snowfall, the clay-rich high-grade ore turned sticky, and the plant switched to lower-grade sulfide stockpiles — a compounding hit to both grade and recovery. It is the kind of explanation an investor can accept once. What makes this quarter different is that Ball said out loud what the sell side has been thinking: “you probably have thinking to yourself, I've heard this before from this company, you promise me you're going to make changes and you put out another unacceptable quarter” — Ian Ball, Executive Vice Chairman · 2026-11-10.There was a lack of oversight that we mentioned in our press release. From there, a lack of detail, there was delayed decision-making, and from there, we made a number of personnel changes.
The calendar keeps sliding right
While the gold mines stumbled, the copper option — the asset that actually drives McEwen's valuation — quietly moved further away. The trajectory of the Los Azules schedule is now a pattern rather than an event. In November 2025 the IPO was “sometime next year” — Robert McEwen, Chairman and Chief Owner · 2025-11-06. By August 2026 it had firmed to “the latter part of this year” — Rob McEwen, Chairman and Chief Owner · 2026-08-06. On this call it has no date at all: preparations “continue in parallel” while full project financing and FID are now targeted for mid-2027, with the updated technical report pushed to February 2027.Michael Meding called it a one-in-25-year event and is buying back time with money — expanding the construction camp to 3,000 beds from 2,500. The site access clause is doing a lot of work in that sentence, and management is honest that the 2030 first-copper target now depends on it. Note too what has not slipped: the FID work is off-site, the environmental approval for the grid connection is in hand, 97% of surveyed neighbours accept the project, and McEwen Copper still holds $157.8 million of cash against a term loan now upsized to $240 million. The bridge is funded. The bridge is not the mine.The Andes had the heaviest snowfall in more than 2 decades, and it has delayed the reopening of our access road. Road crews expect to reach site in early 2027.